Demo Questions

Question 1
How should a Development Team deal with non-functional requirements?
  1. Ensure every Increment meets them.
  2. Make sure the release department understands these requirements, but it is not the Development Team’s responsibility.
  3. Handle them during the Integration Sprint preceding the Release Sprint.
  4. Assign them to the lead developers on the team.
Correct answer: A
Question 2
When is a Sprint over?
  1. When the Product Owner says it is done.
  2. When all Product Backlog items meet their definition of “Done”.
  3. When all the tasks are completed.
  4. When the time-box expires.
Correct answer: D
Question 3
Scrum has a role called “Project Manager”.
  1. True
  2. False
Correct answer: B
EXAM SIMULATOR

How to Open TQB Files?

Use Taurus Exam Simulator to open TQB files

Taurus Exam Simulator


Taurus Exam Simulator for Windows/macOS/Linus

Download

Taurus Exam Studio
Enjoy a 20% discount on Taurus Exam Studio!

You now have the chance to acquire Exam Studio at a discounted rate of 20%.

Get Now!
-->